DEFINITY Enterprise Communications Server Release 6 | Issue 5 |
Installation and Test for | May 1998 |
1 Install and Connect Cabinets |
|
Connect AC Power and Ground | Page |
|
|
6.At the AC load center, connect a 10 AWG (#25) (6 mm2) wire to the
AC Load Center is More Than 50 Feet (15.2 m) from Cabinet
1.Mount the
2.At the bottom rear of the PPN cabinet, connect a 6 AWG (#40) (16 mm2) CABINET GROUND wire to the cabinet ground block. See Figure
3.Route the wire to the
4.At the first EPN cabinet (if provided), connect a 6 AWG (#40) (16 mm2) CABINET GROUND wire to the cabinet ground terminal block.
5.Route the CABINET GROUND wire to the
![]()
NOTE:
If the EPN cabinet is located remote from the PPN cabinet (in a separate room or building), route the EPN CABINET GROUND wire to an approved ground.
6.Repeat connecting each EPN cabinet to the
7.Connect a 6 AWG (#40) (16 mm2) ground wire to an unused terminal on the
8.Route the ground wire to the AC load center ground and connect.