Lucent Technologies Release 6 manual Perform tests

Models: Release 6

1 453
Download 453 pages 12.94 Kb
Page 265
Image 265

DEFINITY Enterprise Communications Server Release 6

Issue 5

Installation and Test for Multi-Carrier Cabinets 555-230-112

May 1998

 

 

5Install and Wire Telephones and Other Equipment

Add Packet Bus to R6si

Page 5-114

3.At each EPN, install the appropriate circuit packs. See Table 5-21.

4.Power up EPN2, then EPN1, then the PPN as required.

5.Enter change system-parameters maintenance and press Enter. Use this form to enable the packet bus.

6.Perform tests.

Table 5-21. Circuit-Pack Locations for Packet Bus in Each EPN

Circuit Pack

Carrier

Quantity

Slot

 

 

 

 

TN570

Expansion Control Carrier A

1 or 21

EXPN INTFC/1 and /2

TN771C

Expansion Control Carrier A

12

Any Available Port Slot

1.Quantity of this pack should equal the number of EPNs.

2.Optional for digital trunk testing.

Resolve Alarms

Examine the alarm log. Resolve any alarms that may exist using DEFINITY

Enterprise Communications Server Release 6 Maintenance for R6vs/si.

Contact INADS to Enable Customer Options and

Verify Alarm Origination

Be sure the system is part of the existing INADS database by calling the INADS Database Administrator at the Technical Service Center (TSC). Verify that INADS can dial into the system and that the system can dial out to INADS.

As part of the system registration process, the INADS Database Administrator enables Alarm Origination and enables customer options.

! CAUTION:

If you do not enable Alarm Origination when the customer has purchased a services contract, the system cannot report any alarm to the TSC automatically, causing the TSC to be unable to fulfill the services contract.

Page 265
Image 265
Lucent Technologies Release 6 manual Perform tests