DEFINITY Enterprise Communications Server Release 6 | Issue 5 | ||
Installation and Test for | May 1998 | ||
1 Install and Connect Cabinets |
|
| |
| Connect AC Power and Ground | Page | |
|
|
|
|
|
|
|
|
Figure Notes
1.Connect small battery holdover cable (or temperature sensor cable from large battery cabinet) to J20
2.Carrier Circuit Breakers
3.Ground Terminal Block
4.Connect large battery holdover cable here
5.
6.
7.1/0 AWG (50 mm2) 50 feet (15.2 m) cable to large battery cabinet. For cables greater than 50 feet (15.2 m), contact your Lucent Technologies representative.
8.Ground Terminal Block
9.To AC load center or approved
Figure 1-4. Power Distribution Unit (J58890CH)
2.Be sure the main power to the power distribution unit is OFF.
3.At the power distribution unit, set all carrier circuit breakers OFF.