DEFINITY Enterprise Communications Server Release 6 | Issue 5 |
Installation and Test for | May 1998 |
1 Install and Connect Cabinets |
|
Earthquake Protection Installation | Page |
|
|
8.A
Measure the distance from 1 of the anchors to the bottom of the cabinet. Add
9.When all 4 threaded rods are cut, replace the raised floor panels removed in Step 5.
10.Position the cabinet over the holes and adjust the leveling legs until the cabinet is level.
![]()
NOTE:
If the system is supplied with cable ductwork, the cabinets must be level from front to rear and from side to side. They must be square with respect to each other to within +
11.Insert the threaded rods through the cabinet bottom and thread into the concrete floor anchors.
12.Place a
13.Repeat this procedure for each cabinet to be installed (including the Auxiliary Cabinet and the Stratum 3 Clock Cabinet).