1 Install and Connect Cabinets

 

Earthquake Protection Installation

Page 1-36

 

 

8.A 3/8-16 threaded rod (part number 845557073) is used to secure the cabinet to each concrete floor anchor. See Figure 1-14.

Measure the distance from 1 of the anchors to the bottom of the cabinet. Add 1/2-inch (1.3 cm) to this measurement to allow the rod to be threaded into the floor anchor. Add an additional 1/2-inch (1.3 cm) to allow the rod to protrude up through the bottom of the cabinet. For example: if the distance from the floor anchor to the bottom of the cabinet is 10 inches (25 cm), cut the threaded rod 11 inches (27.9 cm) long.

9.When all 4 threaded rods are cut, replace the raised floor panels removed in Step 5.

10.Position the cabinet over the holes and adjust the leveling legs until the cabinet is level.

NOTE:

If the system is supplied with cable ductwork, the cabinets must be level from front to rear and from side to side. They must be square with respect to each other to within + -1/8-inch (0.3 cm).

11.Insert the threaded rods through the cabinet bottom and thread into the concrete floor anchors.

12.Place a 3/8-inch flat washer onto each rod. Thread a 3/8-16 hex nut onto each rod and tighten securely.

13.Repeat this procedure for each cabinet to be installed (including the Auxiliary Cabinet and the Stratum 3 Clock Cabinet).