a. The Framing Mode: field is display only and shows the hardware setting.
b. The
c. In the Facility A Circuit ID: field, enter an optional facility name that is unique to each facility (up to 40 alphanumeric characters). Press Enter.
d. A display similar to the following appears after the fiber link administration is completed:
RESET
E1 Installations Only
a.Enter y or n in the CRC? field. The “CRC” means Cyclic Redundancy Check. This is an error detection algorithm.
b. The Line Termination: field is display only. A 75 (75 Ohms) or 120 (120 Ohms) typically displays.
c. In the Facility A Circuit ID: field, enter an optional facility name that is unique to each facility (up to 40 alphanumeric characters). Press Enter.
d. A display similar to the following appears after the fiber link administration is completed:
RESET
All Installations
1.When the system reset is finished, enter the status
2.A Span LED, on the front of the DS1 Converter circuit pack, must be on for each active facility administered. For example, if Facility A and Facility B are administered, then the top 2 Span LEDs on the circuit pack must be on (yellow). The yellow LEDs are on only if no problems were encountered during the administration of hardware. Span LEDs associated with