2Install Telecommunications Cabling

Install Equipment and Cables

Page 2-6

Install Equipment and Cables

Hardware Installation

The following procedures assume 1 system technician is performing the installation. Procedures are provided for installing the following:

■Main Distribution Frame (MDF)

■Cable Slack Managers

■Sneak Fuse Panels

■Labels for the Main Distribution Frame

Install the Main Distribution Frame

The preferred MDF location is directly behind the system cabinets.

Wall Mounting 110A-Type Terminal Blocks

The 110A-type hardware can be stacked in almost any arrangement at any height or location on the wall. One arrangement is shown in Figure 2-3. The distance between the mounting screw holes on the terminal blocks is 10.81 inches (27.4 cm). If a vertical patch cord trough is used, the distance between the mounting screw holes is 5.31 inches (13.3 cm).

Page 59
Image 59
Lucent Technologies Release 6 Install Equipment and Cables, Hardware Installation, Install the Main Distribution Frame