5Install and Wire Telephones and Other Equipment

Add the Fiber Optic Cable

Page 5-84

 

 

lcda4fop RPY 021398

Figure 5-40. Dress the Cable

15.If a circuit pack was removed to access 2 open slots (from ‘CabinetPreparation’’ on page 5-72), replace the circuit pack into its original slot.

16.Close the front door.

17.Discard the pass-thru tool.

Test the Installation

1.Login to the management terminal.

2.Administer the system by referring to the ATM section of the Installation and Test for Adjuncts and Peripherals, 555-230-125.

3.Enter list configuration all to determine if the new circuit pack appears in the correct slot and that there are no circuit pack conflicts.

Page 235