DEFINITY Enterprise Communications Server Release 6 | Issue 5 |
Installation and Test for | May 1998 |
|
|
2Install Telecommunications Cabling
Install Cable Slack Managers | Page |
Install Cable Slack Managers
1.Place the Z113A Cable Slack Manager against the wall under the MDF. See Figure
2.Place the next cable slack manager beside the previously installed unit. Align the tabs and interlocks and snap the units together.
3.Repeat Step 2 until all cable slack managers are installed.
![]()
NOTE:
Nine
Holes are provided in the sides of the base for bolting cable slack manager together. Bolts and shims must be obtained locally.
4.The system cables will route through the cable slack manager as shown. Complete cable routing is covered later in this chapter.
cbdfflr CJL 102396
Figure Notes:
1. | System Cabinet | 4. | Spare Center Troughs |
2. | Cable Slack Manager | 5. | Cabinet Trough for Port Cables |
3. | Cable Clamp |
|
|