Configuration 3: R8si<—x.25 —> R8r Gateway

3 C-LAN Administration

<—ethernet—> R8si

 

Configuration 3: R8si<—x.25 —> R8r Gateway <—ethernet—> R8si

In this configuration, a DEFINITY ECS R8r acts as a gateway between two other nodes — one connected via X.25 to an R8si and the other via ethernet to another R8si.

Switch 1

PGATE DS1

PDM

DEFINITY

ECS R8r

C-LAN

Switch 2

DEFINITY ECS

R8si

BX.25

 

PI

 

 

 

 

 

Switch 3

node-1

Hub

C-LAN

 

Ethernet node-3

DEFINITY ECS R8si

Task Summary

The following tasks need to be completed for Switch 1, Switch 2, and Switch 3:

1Review checklist

2Switch 1 administration

a Assign node names

b Assign pdm data module c Assign IP Interfaces

d Assign link (via an x.25 data module) to Switch 2

e Assign link (via an ethernet data module) to the LAN f Assign processor channels

3Switch 2 administration

a Assign link (via a proc-intf data module) to node 1 b Assign processor channels

4Switch 3 administration

a Assign node names b Assign IP Interfaces

c Assign link (via an ethernet data module) to the LAN d Assign processor channels

5Enable links and processor channels

Administration for Network Connectivity

 

 

555-233-504 — Issue 1 — April 2000

CID: 77730

99

Page 119
Image 119
Lucent Technologies Release 8.2 manual R8si BX.25, Hub, Ethernet node-3 Definity ECS R8si