Configuration 4: R8csi <—ISDN—> R8si Gateway

3 C-LAN Administration

<—ppp—> R8csi

 

Switch 3 Task — Assign Link via ppp Data Module to Switch 1

This task administers a ppp data module on Switch 3 for the ppp connection to Switch

1.The data module associates a link number with a port address, extension number, and node name for the C-LAN port used for this connection.

Steps

Begin

> Open Data Module form — enter ad da n

add data-module next

Page 1 of x

 

 

DATA MODULE

 

 

Data Extension: 2801

 

 

 

 

 

Name: _ppp on link 1 to node-1___

BCC: 2

Type: ppp

 

 

 

 

 

COS: 1

 

 

 

 

 

 

 

 

 

 

 

 

 

Port: 01a0906

 

 

 

 

 

COR: 1

 

 

Link: 1_

 

 

 

 

 

TN: 1

 

 

Enable Link? n

 

 

 

 

 

 

 

 

Node Name: node-3

 

 

____

 

 

 

 

 

 

 

 

 

 

 

Subnet Mask: 255.255.255.0

 

 

Establish Connection: n

 

 

 

 

 

 

 

 

DESTINATION

 

 

 

 

 

 

 

 

Digits:

 

________

 

 

 

Node Name: node-1_________

 

 

CHAP? n

 

 

 

 

 

 

 

 

 

 

 

 

[This data module is assigned the extension 2801; you can assign any unused

extension in the dial plan.]

 

 

> Enter values

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Field

 

 

 

 

 

Conditions/Comments

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Type:

 

 

 

 

 

This indicates the data-module type for this connection.

 

 

 

 

 

 

 

 

 

 

 

 

 

Port:

 

 

 

 

 

In this example, the C-LAN circuit pack is in slot 01a09; the

 

 

 

 

 

 

 

 

 

ppp connection is through port 06.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Link:

 

 

 

 

 

The link number must be in the range 1 – 25 (for R8csi), not

 

 

 

 

 

 

 

 

 

previously assigned on this switch.

 

 

 

 

 

 

 

 

 

 

 

 

Enable Link?

 

 

 

If you need to add an IP route that uses this node as a

 

 

 

 

 

 

 

 

 

gateway, this field must be set to y before adding the IP route.

 

 

 

 

 

 

 

 

 

Otherwise leave this field set to n until the link administration

 

 

 

 

 

 

 

 

 

is complete; that is, until after all data modules and the

 

 

 

 

 

 

 

 

 

processor channels are assigned, then set to y.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Name:

 

 

 

 

 

Information-only; appears in list generated by the “list data

 

 

 

 

 

 

 

 

 

module” command.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1 of 2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Administration for Network Connectivity

 

 

 

 

 

 

 

 

555-233-504 — Issue 1 — April 2000

 

 

 

 

 

CID: 77730

141

Page 161
Image 161
Lucent Technologies Release 8.2 manual Switch 3 Task Assign Link via ppp Data Module to Switch