GENERAL DESCRIPTION

Holidays may be programmed up to 365 days in advance. On a holiday, special call routing is in effect for up to eight time-of-day changes. Three different holiday schedules, one of which is used on any particular holiday, may be programmed for each tenant.

OPERATING PROCEDURE

See Time of Day/Week Routing - ACD [T-50A].

SERVICE CONDITIONS

1.Holiday schedule routing takes place only for those pilot numbers which route to week routing. If a pilot number routes directly to a Call Control Vector (CCV), its routing is not affected on a holiday even if holiday routing has been programmed.

2.All incoming ACD traffic must follow the same routing (CCV handling) on a holiday.

PROGRAMMING

Refer to Assignment of ACD Holiday Schedule in Chapter 7.