2 Installing a Brocade
•The empty device weighs approximately 362 lbs. You will need a mechanical device (such as a material lift), and at least two people to guide the device into place.
•Before you install the device, make sure that the rack is in a permanent location and is secured to the floor or wall of the building. The installation site must allow adequate clearance for airflow, installation, and maintenance.
Tool requirements and parts list
You will need the following tools to install a
•A forklift or pallet jack to move the router while it is on the pallet (500 lbs. minimum).
•
•A mechanical lift tool fitted with a lift plate (instead of forks) to move the device off the pallet and transport it to the rack. The lift should be rated for 500 lbs. minimum.
•A strap to secure and stabilize the device while it is being moved on the mechanical lift
•A power drill with the following attachments:
-Large #2 Phillips screwdriver attachment
-A 7/16 inch socket wrench attachment
-Large 3/8 inch flat blade screwdriver attachment
Preparing the installation site
Before installation, plan the location and orientation of the device relative to other equipment in the rack. For cooling purposes, allow a minimum of six inches of space between the front and back of the device, and walls or other obstructions.
Because you will need to use a mechanical lift to move and install the device, make sure you allow enough space to operate the lift. You will also need at least two people to slide the router off the lift and into the rack.
Preliminary rack mount installation steps
Follow these initial steps to mount a
1.Ensure the rack is in a permanent location and is secured to the building. Ensure that the installation site allows adequate clearance for airflow, installation, and maintenance.
2.Move the pallet and router as close to the installation site as possible.
3.Remove the chassis from the shipping pallet.
4.Position the mechanical lift equipped with a lift plate as close to the front of the router as possible. Adjust the lift plate height so that it is even with the bottom of the router.
5.Slide the router onto the lift plate.
DANGER
Four or more people are required to position the unpopulated router into the rack.
112 | Brocade MLX Series and NetIron XMR Hardware Installation Guide |
|
|