1152700 • Issue 1 • February 2001 • Operation and Maintenance
DLP-791
Page 3 of 7
12.Set the leaf endpoint parameters as needed. The VCI numbers are not configurable as all leaf endpoints share the same VCI ids. Refer to Table
13.The system responds “Successfully Added Leaf to Connection”. Click on OK to finish.
14.Click on Close to close the Add Leaf window and return to the Connection Configuration window.
15.Repeat steps 11 though 14 for any other leaves that need to be added.
Stop! You have completed this procedure.
Cellworx Vision Subnetwork Management System | ||
File Configuration Fault Performance | ||
Time and Date |
| |
Connection | Create... | |
| ||
Topology | View ... | |
Software | Configure Traffic Contract ... | |
Configure Service Provider Profile ... | ||
NMIC Platform | ||
View Ring Resource Usage ... | ||
| ||
| View Fiber Bandwidth Usage ... | |
|
Figure 791-1. GUI Connection Menu Tree
Page