ADCP-70-220 Issue 1 November 2000 Section 2 Operation and Maintenance

NTP-005

Page 2 of 2

Note: The shelf controller in slot 1 on the expansion shelf will begin to download. The shelf controller does not need to download completely before proceeding to the next step.

7.If using a 1+1 protection configuration, create a bi-directional protection group at the ring NE for a working and protect pair

hosting the expansion shelf, otherwise continue.

DLP-765

8.Return to the GUI main screen by hitting Close on each window opened.

9.Add the STN-EPS shelves to the system using the Cellworx

Vision GUI.

DLP-712

10.Change the system name and location to a unique value for the expansion shelf. At this point the user may also want to properly configure the various settings for the node. This may include

timing configuration, locking ports to remove LOS alarms,

 

configuring the max VC bits to greater than zero to allow VC

 

connections for each port, etc.

NTP-006

11.If using a 1+1 configuration, create a bi-directional protection group at the EPS for the working and protect shelf expansion

interface cards linking to the ring NE, otherwise continue.

DLP-765

12.Choose the update topology button on the GUI to refresh the screen. The NEs should display the new name of the expansion

shelf.

DLP-718

13.Repeat steps 3 through 12 for each STN-EPS shelf.

14. Perform acceptance tests on the new nodes.

NTP-011

Stop! You have completed this procedure.