11 - 31

MELSEC-Q
11 MANUAL CONTROL
11.4.2 Manual pulse generator operation execution procedure

The manual pulse generator operation is carried out by the follow ing procedure.

Write the sequence program created in STEP 1 and
STEP 2 to the PLC CPU using GX Developer.
Using GX Developer, set the control data and create a
sequence program to enable/disable the manual pulse
generator operation. (Set the control data in the QD75
buffer memory using the TO command.)
One of the following two methods can be used.
<Method 1>
Directly set (write) the parameters in the QD75 using
GX Configurator-QP.
<Method 2>
Set (write) the parameters from the PLC CPU to the QD75
using the sequence program (TO command).
STEP 1
Manual pulse
generator operation
start
End of control
STEP 2
STEP 3
STEP 4
STEP 5
Issue a command to enable the manual pulse generator
operation, and input the signals from the manual pulse
generator.
End the input from the manual pulse generator,
and issue a command to disable the manual pulse
Manual pulse
generator operation
stop
STEP 6
Monitor the manual pulse generator operation.
Preparation
Refer to Chapter 5
and Section 11.4.3.
Refer to Section
11.4.4.
Set the parameters
Write the sequence program to the PLC CPU.
One of the following two methods can be used.
<Method 1>
Monitor using GX Configurator-QP.
<Method 2>
Monitor using GX Developer.
Monitoring of the
manual pulse
generator operation
Set " Cd. 20 Manual pulse generator 1 pulse input
magnification". (control data setting)
to
)
Pr.1 )
Pr.24
Create a sequence program in which the enable/disable is
(" Cd. 21 Manual pulse generator enable flag" setting.)
set for the manual pulse generator operation.
Stop operating the manual pulse generator, and write "0"
in " Cd. 21 Manual pulse generator enable flag".
Write "1" in " Cd.21 Manual pulse generator enable
flag", and operate the manual pulse generator.
REMARK

Mechanical elements such as limit switches are considered as already installed.

Parameter settings work in common for all c ontrol using the QD75.