9MAJOR POSITIONING CONTROL

[2]Continuous positioning control

MELSEC-Q

(1)The machine always automatically decelerates each time the positioning is completed. Acceleration is then carried out after the QD75 command speed reaches 0 to carry out the next positioning data operation. If a dwell time is designated, the acceleration is carried out after the designated time elapses.

(2)In operation by continuous positioning control (operation pattern "01"), the next positioning No. is automatically executed. Always set operation pattern "00" in the last positioning data to complete the positioning.

If the operation pattern is set to positioning continue ("01" or "11"), the operation will continue until operation pattern "00" is found.

If the operation pattern "00" cannot be found, the operation may be carried out until the positioning data No. 600. If the operation pattern of the positioning data No. 600 is not completed, the operation will be started again from the positioning data No. 1.

Positioning continue (01)

Positioning continue (01)

Address (+) direction

 

 

Dwell time

 

Address (-) direction

not designated

 

 

 

 

Positioning

 

 

complete (00)

Positioning start signal

ON

OFF

 

[Y10, Y11, Y12, Y13]

Start complete signal

ON

 

[X10, X11, X12, X13] OFF

 

 

ON

BUSY signal

[XC, XD, XE, XF] OFF

Positioning complete signal

ON

OFF

 

[X14, X15, X16, X17]

 

Dwell time

Time

Fig. 9.2 Operation during continuous positioning control

9 - 7

Page 307
Image 307
Mitsubishi Electronics QD75D, QD75P user manual Continuous positioning control, Start complete signal X10, X11, X12, X13 OFF