4.1Connection to Remote I/O Station in MELSECNET/ H Network System
4.1.1Direct CPU connection (Direct CPU connection to the remote I/O station)This section explains the direct CPU connection that connects the GOT to the remote I/O station of the MELSECNET/H network system.
The following shows an example of connecting the GOT to the remote I/O station of the MELSECNET/H network system.
Monitor target
| module | supplyPower | Q25PRHCPU | |
Control system | ||||
|
|
| ||
(System A) |
|
|
|
Network No. 1, Station No. 0 (Multiplexed remote master station)
QJ71BR11 | QJ61BT11N | Empty | supply Power module | Q25PRHCPU |
Network No. 1, Station No. 1 (Multiplexed remote sub master station)
QJ71BR11 | QJ61BT11N | Empty |
Standby system
(System B)
MELSECNET/H remote I/O network
Network No. 1, Station No. 2 (Remote I/O station)
supply Power module | QJ71C24N | Empty | Empty |
CPU direct connection
GOT
(1)Connection method
Connect the GOT to the
For details, refer to the following.
(2)GT Designer3 setting
Set GT Designer3 as follows.
Setting item | Settings | Model | |
|
|
| |
Controller Type |
|
|
|
|
|
| |
Device setting | Host | Host |
|
Remote master | Other (NW No. 1 (network No. of remote I/O network), |
| |
(Network setting) |
| ||
station | Station No. 0 (master station)) |
| |
|
| ||
Q Redundant Setting |
| Do not set the item. |
|
In this case, the GOT monitoring is performed by transient transmission of the MELSECNET/H network system.Therefore, a longer
For displaying objects with a shorter
(3)Monitoring target change when system switching occurs in a redundant system
When the system switching occurs, the multiplexed remote sub master station switched to the control system takes over the master operation of MELSECNET/H.
Since the GOT monitors the master station, the monitoring target is automatically changed to the PLC CPU that is operating as the master.
4 - 8 | 4. HOW TO MONITOR REDUNTANT SYSTEM |
| 4.1 Connection to Remote I/O Station in MELSECNET/H Network System |