Chapter 3 Getting Started

Deployment

Performing Pre-deployment

Say that you are expecting the following hardware:

Cisco 12016 chassis and GRP(s)

ATM and POS line cards (with respective interfaces)

To perform both manual pre-deployment and offline configuration, proceed as follows:

Step 1 Manually deploy a site object. See “Manually Deploying a Generic Site Object” section on page 3-10for further details.

Step 2 Manually deploy the Cisco 12000 Series Router chassis under a site. See “Manually Deploying a Cisco 12000/10720 Chassis” section on page 3-20for further details.

Step 3 Manually deploy GRP(s). See “Manually Deploying a GRP Card” section on page 3-31for further details.

Step 4 Manually deploy the ATM line cards. ATM interfaces are deployed simultaneously. See “Manually Deploying Line Cards” section on page 3-38for further details.

Step 5 Manually deploy the POS line cards. POS interfaces are deployed simultaneously. See “Manually Deploying Line Cards” section on page 3-38for further details.

Now you have pre-deployed and thus created representative objects in Cisco 12000/10720 Router Manager for your expected hardware, modules, and interfaces. All of these objects will be in the Decommissioned state.

Cisco 12000/10700 v3.1.1 Router Manager User Guide

 

OL-4455-01

3-59

 

 

 

Page 113
Image 113
Cisco Systems 12000/10700 V3.1.1 manual Performing Pre-deployment