DEFINITY ECS Release 8.2 Maintenance for R8.2csi
555-233-119 Issue 1
April 2000
Maintenance Objects
3-879PE-BCHL (PRI Endpoint Port)
3
Audit and Update Test (#36)
This test sends port level translation d ata from the switch processor to the U DS1
interface circuit p ack to ensure that the por t’s translation is correct. The por t audit
operation verifies the consistenc y of the current state of the port that is kep t in the
UDS1 interface circuit pac k and in the switch software.
2000 ABORT Response to the test request was not received within the allowable time
period.
2100 ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals a maximum of 5 times.
Any FAIL The NPE of the tested port did not c onference the tones correctly. This causes
noisy and unreliable c onnections.
1. Replace the circuit pack. Even though wideb and calls do not use the
conferencing feature on the NPE, this failure indicates problems with the
circuit pack hardware.
PASS The port can correctly conference multiple connec tions. User-reported
troubles on this port should be investigated by using the other port tests and
by examining the terminal adapter or the external wiring.
Table 3-379. TEST #7 Conference Circuit Test — Continued
Error
Code
Test
Result Description/Recommendation
Continued on next page