DEFINITY ECS Release 8.2 Maintenance for R8.2csi
555-233-119 Issue 1
April 2000
Maintenance Objects
3-75AN-LN-PT (Analog Line Port)
3
System technician-demanded tests: descriptions
and error codes
Always investigate tests in the order p resented in the table below whe n
inspecting errors in the sy stem. By clearing error cod es associated with the
Battery Feed Test,
for example, you may also clear errors g enerated from other
tests in the testing sequenc e.
Order of Investigation
Short Test
Sequence
Long Test
Sequence D/ND1
1. D = Destructive; ND = Nondestruc tive
Battery Feed Test (#35) X X ND
Station Present Test (#48) X X ND
Looparound Test (#161) X ND
Conference Test (#7) X ND
NPE Crosstalk Test (#6) X ND
Station Status and Translation Audits and
Updates Test (#36) XXND