DEFINITY ECS Release 8.2 Maintenance for R8.2csi
555-233-119 Issue 1
April 2000
Maintenance Objects
3-1240UDS1-BD (UDS1 Interface Circuit Pack)
3
2100 ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals for a maximum of 5 times.
2 FAIL The CLJ-LB test failed because it was not set up properly. The UDS1 interface
pack could not successfully p ut the CPE loopback jack into loopback mode.
1. Rerun the test ds1-loop UUCSS cpe-loopback-jack-test-begin
command.
2. If the test continues to fail, the problem could be with the TN464F board,
the CPE loopback jack eq uipment, or somewhere between. Run the test
ds1-loop UUCSS ds1/csu-loopback-tests command to determine if the
loopback tests that are closer to the TN464F board are successful. If any
of these tests fail, follow the maintenance strategy that is associated with
the test that fails.
3 FAIL The CPE Loopback Jack Test was not set up properly. The framed 3-in-24 test
pattern, generated by the UDS1 Interface circuit pac k and looped back
through the CPE Loopback Jack, could not be detec ted properly by the UDS1
circuit pack.
1. Retry the
test ds1-loop UUCSS cpe-loopback-jack-test-beg in
command.
2. If the CPE Loopback Jack test continues to fail, the problem could be with
the TN464F board, the CPE Loopback Jack equipment, or somewhere in
between. Run the
test ds1-loop UUCSS ds1/csu-loopback-tests
command
to see if the loopback tests closer to the TN464F board are successful. If
any of those loopback tests fail, follow the maintenance strategy
associated with those l oopbacks.
Table 3-531. TEST #1212 CPE Loopback Jack Test — Continued
Error
Code
Test
Result Description/ Recommendation
Continued on next page