Maintenance Commands
2-365test port
2
test port

This command performs hard ware diagnostic tests on an ind ividual port c ircuit.

In most cases, tests are performed on hardware connected to the port.

!WARNING:

Since the “clear long ” options clear all c ounters if tests pass, it is poss ible

for firmware counters to be c leared even when a problem exists. In so me

cases customer servic e might degrad e since calls may be routed over

defective equip ment.
Action/
Object Qualifier Qualifier Description Permissions Defaults
Feature
Interactions
test port
location
short
long
repeat
number
clear
schedule
PCSSpp
Option for a brief series of
nondestructive diagnostic tests .
Option for a longer, more
comprehensive series of both
destructive and nondestruc tive
diagnostic tests.
How many times each test in the
sequence is repeated (1-100)
This option causes the test
sequence (short or long) to repeat
until the alarm (if any) is cleared or
a single test in the sequence fails.1
Command is validated and then a
scheduling form disp lays to
schedule execution of the
command. The command is then
placed in the command q ueue and
is executed at the specified time.
The information displayed by the
command is sent to the system
printer instead of the screen.2
Examples:
test port 01c1101 l
test port 01c1101 l schedule
test port 02e1502 sh r 2
test port 02d1201 r 4
test port 01c1101 c
1 If no alarms are registered against the maintenance object then the test sequence is run only onc e. The
long
clear
option forces a clear of all alarms if no errors are encountered d uring testing. The
short clear
option only
clears alarms pertinent to tests in the short sequence. SEE WARN ING BELOW.
2 Refer to the Report Scheduler and System Printer feature specification for more details.
init
inads
craft
Test
Sequence
= short;
Repeat =
1
none