DEFINITY Enterprise Communications Server Release 7
Maintenance for R7r
555-230-126 Issue 4
June 1999
Maintenance Object Repair Procedures
9-324BRI-PORT (ISDN-BRI Port), ABRI-PORT (ASAI ISDN-BRI Port)]
9
1 FAIL Received a status of Level 1 Pendi ng Activation-Endp oint Idle which
indicates a problem with the BRI endpoint or ASAI or Lucent adjunct, the
wiring to the endpoint or adjunct, or the ISDN-BRI port.
For the TN2198, received a status of Level 1 Pending Activation. U interface
down, which indicates a problem with a connection b etween the switch and
the NT1.
NOTE:
An NT1 is a 2-to-4 wire converter that is used to connec t 4-wire
Lucent terminals to a 2-wire TN2198 circuit pack. The NT1 also has
status lamps to determine the health of the unit.
1. For the TN556, verify that an end point is connected to the port. If an
endpoint is connected to the port then proc eed to step 2. For the
TN2198 verify that the connections are good between the switch and
the NT1. Verify that the NT1 has power.
2. As necessary, check and repair the wiring between the c ircuit pack and
the endpoint or adjunct. If a TN2198 is used the set must have been
plugged in for at least 15 seconds before it will stabilize. Execute the
test port PCSSpp command, and review the res ults of the Level 1
Status Inquiry Test to verify the repair. If this test is still failing, proceed
to Step 3.
3. For BRI endpoints, replace the BRI endpoint(s) connected to the p ort or
the NT1 if a TN2198 is used. For ASAI or Lucent adjuncts, follow the
recommended repair procedures of the manufacturer for link
communication problems. For the NT1, follow the manufacturers repair
procedures. Then execute the test port PCSSpp command and review
the results of the Level 1 Status Inquiry Test to verify repair. If this test is
still failing, proceed to Step 4.
4. Escalate the problem to the next tier.
Table 9-143. TEST #621 Level 1 Status Inquiry — Continued
Error
Code Test
Result Description/ Recommendation
Continued on next page