9-1588SYNC (Synchronization)
9
System Technician-Demanded T ests: Descripti ons
and Error Codes
Always investigate tests in the order p resented in the table below when
inspecting errors in the system .
If Stratum 3 is administered via change synchronization, the Stratum 3 Clock
Alarm Query test (test #649) will also execute wh en the test synchronization
command is run. Test 649 is described in the STRAT-3 section.
Test Synchronization Test (#417)
This test updates all the Synchronization Maintenanc e component circuit p acks
with the correct information reg arding their role in provid ing synchronization for
the system. All the Tone-Clock, Expansion Interface, DS1 Interface and UDS1
Interface circuit p acks in the system are updated via this test. This test will either
pass or abort.
Order of Investigation Short Test
Sequence Long Test
Sequence D/ND1
1. D = Destructive, ND = Non-d estructive
Test Synchronization Test (#417) X X ND
Table 9-598. TEST #417 Test Synchronization Test
Error
Code Test
Result Description/ Recommendation
1000 ABORT System resources required to run this test are not available.
1. Retry the command at 1-minute intervals a maximum of 3 times.
1115 ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals a maximum of 3 times.
2500 ABORT Internal System Error
1. Retry the command at 1-minute intervals a maximum of 3 times.
PASS The Synchronization Maintenance component circuit pack parameters have
been successfully updated. The system should be synchronized after
successful execution of this test. If synchronization problems still exist, refer to
the Error Log to obtain information regarding the source of the problem.
Continued on next page