DEFINITY Enterprise Communications Server Release 7
Maintenance for R7r
555-230-126 Issue 4
June 1999
Maintenance Object Repair Procedures
9-1896UDS1-BD (UDS1 Interface Circuit Pack)
9
2100 ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals for a maximum of 5 times.
2 FAIL The test failed because it was not set up properly. The UDS1 pack could not
successfully put the far-end CSU into loopback mode.
1. Rerun the test ds1-loop UUCSS far-csu-loopback-test-begin command.
2. If the test continues to fail, the problem could be with the TN464F board,
the CPE loopback jack eq uipment, or somewhere between. Run the test
ds1-loop UUCSS cpe-loopback-jack-test-begin command to determine
if the CPE loopback jack loopback test is successful. If a CPE loopback
jack device is not being used, issue the test ds1-loop UUCSS
ds1/csu-loopback-tests command instead. If the closer loopback test
fails, follow the maintenance strategy associated with that test.
3 FAIL The Far CSU Loopback Test was not set up properly. The framed 3-in-24 test
pattern, generated by the UDS1 Interface circuit pac k and looped back
through the far-end CSU, could not be detected prop erly by the UDS1 circuit
pack.
1. Retry the
test ds1-loop UUCSS far-csu-loopback-test-begin
command.
2. If the Far CSU Loopback test continues to fail with this error code, the
problem could be with the TN464F board, the far-end CSU equipment, or
somewhere in between. Run the
test ds1-loop UUCSS
cpe-loopback-jack-test-b egin
command to see if the CPE Loopback Jack
test which is closer to the TN464F board is successful. (If a CPE Loopback
Jack device is not being used, then run the
test ds1-loop UUCSS
ds1/csu-loopback-tests
command to see if these even closer loopback
tests succeed). If the closer loopback test fails, follow the maintenance
strategy associated with that loopback.
Table 9-700. TEST #1213 Far CSU Loopback Test — Continued
Error
Code Test
Result Description/ Recommendation
Continued on next page