DEFINITY Enterprise Communications Server Release 7
Maintenance for R7r
555-230-126 Issue 4
June 1999
Maintenance Object Repair Procedures

9-421CO-DS1 (DS1 CO Trunk)

9
Port Audit and Update Test (#36)
This test sends port level translation d ata from switch processor to the DS1 Interface circuit p ack to assure that the trunk’s translation is c orrect. Translation updates includ e the following data: trunk typ e (in/out), dial type, timing parameters, and signaling bits enabled. The port audit operation verifies the consistency of the current sta te of trunk.
0NO
BOARD The test could not relate the internal ID to the port (no board).
This result could be due to incorrect translations, no board is inserted, an
incorrect board is inserted, an insane board is inserted, or the b oard is
hyperactive.
1. Check to ensure that the board translations are correct. Use the list
config command, and resolve any problems that are found.
2. If the board was found to be correctly inserted in step 1, issue the
busyout board command.
3. Issue the reset board command.
4. Issue the release busy board command.
5. Issue the test board long command.
This should re-establish the linkage between the internal ID and the port. If
this is not the case, dispatch to check to ensure that there is a valid board
inserted.
NOTE:
Hyperactivity causes some special problems with the sequence
suggested above.If the ports are translated after issuing the list
config command but the ’Vintage’ field reports that there is no board
(when there really is a board), then the busyout board and the
release busy board commands will not work (even though the reset
board command will work). The software will put the hyperactive
board back in service after the hypera ctivity clears.
Table 9-176. TEST #7 Conference Circuit Test — Continued
Error
Code Test
Result Description/ Recommendation
Continued on next page