Maintenance Object Repair Procedures
9-358BRI-SET, ASAI-ADJ, BRI-DAT
9
SPID Facility Test
This test is used to verify the wiring and op eration of the signaling link b etween
the switch and a endp oint or adjunct on a BRI interface. This test is not
executed from the administration terminal, but rather is executed by using a
BRI test set equipped with a display. The test set may replace the BRI set,
ASAI or Lucent adjunct und er test by plugging it into the same jack or by
bridging it onto the wiring at some point between the switc h and the endpoint (or
adjunct), thereby c reating a pseudo-BRI multipoint c onfiguration.
1187 ABORT The circuit pack, port or station may have been busied out by a technic ian.
1. Look in the Error Log for Error Type 18 (busied out ) for BRI-BD,
BRI-PORT, or BRI-SET.
a. If this error type is present for BRI-SET only, then release the station
via the release station
b. If this error type is present for BRI-PORT and BRI-SET, then release
the port via the release port PCSSpp command and run the test
again.
c. If the error is present for BRI-BD, BRI-PORT, and BRI-SET, then
release the circuit pack via the release port PCSSpp command and
run the test again. If the error is present for both BRI-BD and
BRI-PORT, then release the circuit pack via the release board
PPCSS command and run the test again.
NOTE:
When you release the circuit p ack, you release all ports asso ciated
with it. If certain ports still need to be busied out, use the release port
PCSSpp command to busy them out.
2. Make sure the terminal is connected.
3. Retry the command at one-minute intervals a maximum of five times.
4. If the test continues to abort, escalate the problem.
2012 ABORT Internal System Error.
2100 ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at one-minute intervals a maximum of five times.
2. If the test continues to abort, escalate the problem.
PASS The switch has successf ully executed the BRI station aud its.